Project Value: £1,700,000.00
Term: May 2024 – December 2024

The City of Edinburgh Council

The City of Edinburgh Council

26 – 28 Harvesters Way & 69 Dumbeg Park

AC Whyte partnered with The City of Edinburgh Council on a Design & Build project to deliver Fabric Repair Works to 21 properties across 3- and 4-storey blocks at 26–28 Harvesters Way and 69 Dumbeg Park. The project successfully achieved the design criteria maximum target of 0.19W/m²K for the external envelope through the installation of a new External Wall Insulation (EWI) system across all existing wall areas, excluding unheated external walls in common stairwells and internal party walls within shared stairwell spaces.

Collaboration with long-standing manufacturers and the supply chain, combined with the expertise of AC Whyte’s direct EWI and Roofing teams, played a crucial role in delivering the project to a high standard. As the properties remained occupied throughout the works, including kitchen and bathroom replacements, careful planning and continuous communication were essential in minimising disruption to residents.

EPC, Structural, Ecological and Cavity Surveys
Installation of External Wall Insulation (EWI) system
Installation of an insulated single ply deck roof
Remove and renew 21nr kitchens & bathrooms
Asbestos removal works, using a specialist subcontractor
Relocation of internal gas meters in line with SGN standards
Replacement of boilers
Loft and underfloor insulation
Replacement of rainwater goods
Fire stopping
Decoration to communal areas including new vinyl flooring
New Front & Rear Entrance Doors compliant with Secured by Design
Door entry and audio comms installations
Communal IRS System
Ventilation upgrades to meet current regulations
Remedial works to existing glazed cupola
Liquid plastic walkway floors to balconies
Painting to the internal and external walls to compliment the new system
EPC, Structural, Ecological and Cavity Surveys
Installation of External Wall Insulation (EWI) system
Installation of an insulated single ply deck roof
Remove and renew 21nr kitchens & bathrooms
Asbestos removal works, using a specialist subcontractor
Relocation of internal gas meters in line with SGN standards
Replacement of boilers
Loft and underfloor insulation
Replacement of rainwater goods
Fire stopping
Decoration to communal areas including new vinyl flooring
New Front & Rear Entrance Doors compliant with Secured by Design
Door entry and audio comms installations
Communal IRS System
Ventilation upgrades to meet current regulations
Remedial works to existing glazed cupola
Liquid plastic walkway floors to balconies
Painting to the internal and external walls to compliment the new system
Project value: £1,700,000
Timeframe: May 2024 – December 2024
Construction type: Traditional Brick and Residential Blocks
Carbon savings: 22,960kgCO2/yr

THE CITY OF EDINBURGH COUNCIL

The Results

The project delivered significant energy efficiency improvements, reducing carbon emissions and helping to combat fuel poverty for residents.

Upgrades included new roofing, gutters, windows, and doors, alongside the installation of an external wall insulation and rendering system to enhance thermal performance. Common internal and external areas were refurbished, with electrical works carried out to modernise the properties, and existing boilers were replaced to improve heating efficiency. These enhancements created warmer, more comfortable homes while ensuring long-term sustainability and compliance with PAS 2030:2019.